FIELD GUIDE · TENANT IMPROVEMENTS

Common scope gaps in tenant-improvement bids.

Tenant improvements look simple on paper. The new plans show what is being built, and very little about what is already there. These are the gaps that show up most often.

5 min readR&K Construction Solutions

1. Demolition the new plans do not show

New plans show new work. Existing flooring, ceiling grid, wall coverings and abandoned cabling are often left to a single demolition note. Walk the demolition plan against the new finish plan room by room, and price removal of every finish that is being replaced, not only the partitions that are shown dashed.

2. Floor preparation under new flooring

Removing old flooring leaves adhesive, cracks and high spots. Resilient flooring needs a flat, dry substrate, and the specification usually says how flat and how dry. Carry floor preparation as a defined scope, and state in a clarification what is included: grinding, patching, leveling or moisture testing.

3. Transitions and base at every change of finish

Every place two floor finishes meet needs a transition, and every wall needs base. These are small lines, which is exactly why they get dropped. Count transitions from the finish plan doorways and base from the room perimeters, less door openings.

4. Every layer of rated drywall

Rated corridors, demising walls and shafts often call for multiple layers per side. Check the wall type for each rated wall and price each layer. A one-layer price on a two-layer wall is a quiet, expensive error.

5. Blocking and backing

Casework, grab bars, wall-mounted equipment and accessories all need blocking in the wall. It rarely has its own detail, and it rarely makes it into a framing number unless someone looks for it on the elevations.

6. Ceilings: grid, hard lid and soffits

Read the reflected ceiling plan for every ceiling type, not just the main grid. Drywall soffits, bulkheads and ceiling height changes carry framing and finish that the floor plan does not show.

7. Dumpsters, protection and final clean

State how many dumpster pulls are carried, what protection is included for adjacent tenants and finishes, and whether final clean is in your scope. Each is a common source of disagreement once the job starts.

8. Working hours in occupied centers

Retail centers and medical buildings often restrict noisy work, deliveries and dumpster access to after hours. If the lease or the landlord's construction rules limit working hours, the labor price has to reflect it, and the exclusions should say so.

How to protect the bid

Every gap above has the same fix: measure it if the drawings show it, and write it down if they do not. A clarification that says what you assumed is worth more on day one of the job than a lower number was on bid day.

QUICK ANSWERS

Questions we hear often.

What is most often missed in TI bids?

Demolition of existing finishes the new plans do not show, floor preparation, transitions and base, and extra layers at rated walls.

How should after-hours work be handled in a bid?

If the landlord's rules restrict working hours, price the labor accordingly and state the assumption in the exclusions and clarifications.

YOUR NEXT PROJECT STARTS HERE

Bring the plans.
We’ll bring the detail.

Tell us what you’re bidding and when it’s due.
Let’s put a clear scope behind your next number.

Request an estimatePrefer to talk? +1 (602) 516-3601