1. Demolition the new plans do not show
New plans show new work. Existing flooring, ceiling grid, wall coverings and abandoned cabling are often left to a single demolition note. Walk the demolition plan against the new finish plan room by room, and price removal of every finish that is being replaced, not only the partitions that are shown dashed.
2. Floor preparation under new flooring
Removing old flooring leaves adhesive, cracks and high spots. Resilient flooring needs a flat, dry substrate, and the specification usually says how flat and how dry. Carry floor preparation as a defined scope, and state in a clarification what is included: grinding, patching, leveling or moisture testing.
3. Transitions and base at every change of finish
Every place two floor finishes meet needs a transition, and every wall needs base. These are small lines, which is exactly why they get dropped. Count transitions from the finish plan doorways and base from the room perimeters, less door openings.
4. Every layer of rated drywall
Rated corridors, demising walls and shafts often call for multiple layers per side. Check the wall type for each rated wall and price each layer. A one-layer price on a two-layer wall is a quiet, expensive error.
5. Blocking and backing
Casework, grab bars, wall-mounted equipment and accessories all need blocking in the wall. It rarely has its own detail, and it rarely makes it into a framing number unless someone looks for it on the elevations.
6. Ceilings: grid, hard lid and soffits
Read the reflected ceiling plan for every ceiling type, not just the main grid. Drywall soffits, bulkheads and ceiling height changes carry framing and finish that the floor plan does not show.
7. Dumpsters, protection and final clean
State how many dumpster pulls are carried, what protection is included for adjacent tenants and finishes, and whether final clean is in your scope. Each is a common source of disagreement once the job starts.
8. Working hours in occupied centers
Retail centers and medical buildings often restrict noisy work, deliveries and dumpster access to after hours. If the lease or the landlord's construction rules limit working hours, the labor price has to reflect it, and the exclusions should say so.
How to protect the bid
Every gap above has the same fix: measure it if the drawings show it, and write it down if they do not. A clarification that says what you assumed is worth more on day one of the job than a lower number was on bid day.