INSIDE THE DELIVERABLE
See what a clear estimate looks like.
Explore this illustrative trade breakdown. Select a trade to review its scope, quantity, and allowance.
Interior build-out
| Trade / scope | Quantity | Amount |
|---|---|---|
| 1,850 SF | $24,500 | |
| 3 EA | $3,600 | |
| 312 CY | $65,520 | |
| 4,120 SF | $48,500 | |
| 18,600 SF | $84,600 | |
| 7,800 SF | $34,300 | |
| 1,400 SF | $12,650 | |
| 7,900 SF | $67,450 | |
| 1,250 SF | $19,375 | |
| 3,640 LF | $11,830 | |
| 620 SF | $14,850 | |
| 19 EA | $32,350 |
LVT flooring
Luxury vinyl tile with adhesive, layout, transitions, and defined floor preparation. Quantities follow the finish schedule.
Rubber base is priced as its own trade item.
$4.75 / SF
Material allowance within the sample trade total. Final specifications are confirmed for each project.
Largest sample trades
Select a trade to explore · Share of total
Illustrative quantities and pricing from our sample format. This is not a live bid or a project quote.
Demolition
Selective removal of existing finishes and partitions within the indicated work area. Coordinate removals with the demolition plans.
Dumpsters are carried separately.
Not applicable
Material allowance within the sample trade total. Final specifications are confirmed for each project.
Dumpster rentals
Three 30 CY dumpster pulls, including delivery, disposal, and collection.
Additional pulls require a scope adjustment.
Not applicable
Material allowance within the sample trade total. Final specifications are confirmed for each project.
Building concrete
Building footings, slabs, and pads, including reinforcement, forms, placement, curing, and control joints.
Exterior flatwork is carried in site concrete.
Not applicable
Material allowance within the sample trade total. Final specifications are confirmed for each project.
Site concrete & hardscape
Exterior walkways, accessible ramps, and entrance flatwork with subgrade preparation and broom finish.
Curb and gutter are excluded unless identified.
Not applicable
Material allowance within the sample trade total. Final specifications are confirmed for each project.
Wall drywall
Gypsum board for wall assemblies, measured by layer. Includes joint treatment, corner protection, and Level 4 finish.
Wet-area and rated assemblies follow the wall types.
$0.62 / SF
Material allowance within the sample trade total. Final specifications are confirmed for each project.
Ceiling drywall
Gypsum board at hard ceilings and soffits with finish levels appropriate to exposed and concealed locations.
Refer to the reflected ceiling plan for extents.
$0.62 / SF
Material allowance within the sample trade total. Final specifications are confirmed for each project.
ACT ceilings
Suspended 2 × 2 acoustical ceiling system, including grid, supports, perimeter trim, and tile.
Include seismic bracing where required.
$5.50 / SF
Material allowance within the sample trade total. Final specifications are confirmed for each project.
LVT flooring
Luxury vinyl tile with adhesive, layout, transitions, and defined floor preparation. Quantities follow the finish schedule.
Rubber base is priced as its own trade item.
$4.75 / SF
Material allowance within the sample trade total. Final specifications are confirmed for each project.
Porcelain tile flooring
Porcelain floor tile with setting materials, grout, movement joints, and finish transitions.
Restroom wall tile is listed separately.
$6.25 / SF
Material allowance within the sample trade total. Final specifications are confirmed for each project.
Rubber base
Four-inch rubber cove base, including adhesive, corners, and terminations.
Measured along the applicable finished wall perimeter.
$1.65 / LF
Material allowance within the sample trade total. Final specifications are confirmed for each project.
Restroom wall tile
Tile wall finishes with wet-area backing, mortar, grout, trim, and corner detailing.
Coverage follows the interior elevations.
$8.50 / SF
Material allowance within the sample trade total. Final specifications are confirmed for each project.
Doors, frames & hardware
Seven exterior hollow metal doors and twelve interior wood doors with frames and standard commercial hardware.
Storefront assemblies are excluded.
HM $1,500 / EA · Wood $450 / EA · Hardware $275 / EA
Material allowance within the sample trade total. Final specifications are confirmed for each project.
Scope clarifications
Finish selections and quantities follow the drawing schedules. Rated assemblies are counted by layer. Pricing changes when the specified scope changes.
Defined boundaries
This example excludes permits, concealed conditions, hazardous material abatement, and any work outside the stated trade scope. Each actual proposal has project-specific clarifications.
YOUR NEXT PROJECT STARTS HERE
Bring the plans.
We’ll bring the detail.
Tell us what you’re bidding and when it’s due.
Let’s put a clear scope behind your next number.